S-Curve Generator

Construction Cost Distribution

Project — S-Curve Analysis

Total: $1.00MDuration: 12 monthsAvg Monthly: $83K

Project S-Curve

$1.00M over 12 months

MonthMonthlyCumulative%
1$15,750$15,7501.6%
2$39,750$55,5005.6%
3$57,750$113,25011.3%
4$69,750$183,00018.3%
5$89,250$272,25027.2%
6$98,750$371,00037.1%
7$105,750$476,75047.7%
8$110,250$587,00058.7%
9$111,750$698,75069.9%
10$114,250$813,00081.3%
11$104,500$917,50091.8%
12$82,500$1,000,000100.0%
Total$1,000,000$1,000,000100%

Generated 1/9/2026 • Construction S-Curve Analysis